Phase 1 of the Evergreen Project, which included site preparation, power infrastructure, and installation of the bromine tower, was completed in December 2025. Phase 2, which encompasses the major infrastructure and equipment supporting the plant, is currently underway with mechanical completion targeted by the end of 2026. The entire facility is expected to be operational by the end of 2027, with first production anticipated in early 2028.