Three of those unit operations have been commissioned and tested and are undergoing integration to date: the robotic loading arms, the Eddy system, and the washing system. This represents significant progress toward the full commissioning, start-up and continuous operation of the 100,000 ton per year solar panel recycling production line.
Commissioning, and all aspects of integration, tuning, and staged stress-testing will continue through late July 2026, when continuous operations will commence. The first full month of operation will begin within the next two months.