On July 20, 2026, Namib Minerals published a defined five-step pathway and targeted milestone schedule for the restart of Redwing Mine, with dewatering as Step 1 and completion targeted for Q4 2026. That step is now complete, ahead of the targeted schedule.
Completion of dewatering restores safe access to the underground workings, enabling underground mapping, sampling and the geotechnical and hydrological work programmes that feed the technical programme of the Definitive Feasibility Study ("DFS"). The DFS technical programme remains fully funded through to completion and on track to conclude in early Q1 2027, unchanged from the schedule published in July.